What happens next

The Inspector’s recommendation Report was submitted to the Welsh Government on 20/08/2021. The Welsh Ministers normally have up to 12 weeks from this date to issue a decision.

Timeline (9 items)

Transition to new service from 1 October 2021

This site is for viewing only and was last updated on the 16 September. Any queries should go to the Planning and Environment Decisions Wales (PEDW) service. See the announcement on GOV.UK for more information.
28 September 2021
The Inspector’s report sent to Welsh Minister
12 August 2021

This application/examination has been suspended until 05 March 2021.

For more information, please see the Planning Inspectorate’s letter dated 11/12/2020.

11 December 2020
The procedure has been confirmed
11 December 2020
Representations period closed
28 November 2020

The period for representations will close at midnight on the evening of Friday November 27 2020.

25 November 2020

The deadline for the submission of representations has changed from 20 November to 27 November.

23 October 2020
The application has been accepted as valid
16 October 2020
The application has been submitted to the Inspectorate
04 September 2020